The following frequently asked questions could help you better prepare when
Applying for New Service. If you require additional answers to your questions,
please email New Service Installation,
or call 800-242-9772, 7 a.m. to 4 p.m. Monday - Friday (CST).
- How much lead-time should I consider when applying for new service?
-
We suggest you complete our Application for New Service at least one week
before your foundation will be excavated. It is hard to determine the
lead-time for your service installation due to the many variables when
considering a construction schedule. Some of these variables include: delays
due to weather, heavy workloads, equipment breakdown, outages due to storms, etc.
Back to top
- What information do I need to provide when applying for new service?
- When applying for service, the following information is required:
- Name(s) of person to be billed (first name, middle initial and last name)
- Current mailing address and phone number of the person to be billed.
- Service address (if address is not available, the closest neighbor's address or
an electric pole number)
- Employer or source of income
- Social security number or tax ID (optional, but preferred)
- Copy of the septic permit if building in a rural area
- Size of the electric service entrance (amps)
- Signed site sketch/Liability waiver form with the following information included
on the sketch:
- Desired location of the gas and electric meters
- Setback distance from the road
- Well, septic and drain field locations (both primary and alternate)
- Location of future decks, garage or other out buildings
Back to top
- How do I obtain a Site Sketch and Liability Waiver form as well as other forms
that I may need when applying for gas or electric service?
- The forms and references you need when applying
for gas and/or electric service can be found on our website.
Back to top
- Where is the best location for my gas and electric meter? Are there any
requirements?
- The ideal location for the gas and electric meter is 3 feet beyond the corner of
your home. By having the gas and electric meter located together, or being
jointly installed, the installation costs may be reduced or eliminated.
There are code requirements in regard to the location of
your gas meter from windows, make-up air (from appliances like a furnace water
heater), or fresh air intake. Also, the electric meter needs to be at least 3 or
4 feet from the gas meter depending upon the side it's on. We recommend that you
discuss these issues with your electrician or heating contractor in order to
identify the best location for each meter.
Back to top
- Can I run my electric service to the back of the house?
- The customer has the option to run the electric service to just about any
location on the house. When extending the electric service, you should consider
any future additions or modifications to your house, so you avoid additional
costs to relocate that electric facility due to poor planning.
Back to top
- What is the cost for new gas and electric service installation?
- The cost for new service varies depending on a number of factors. Some factors
include the distance from our distribution natural gas pipes or electric lines,
and customer preferences for underground or overhead service and meter location.
Generally, after submitting an application for service and a site
sketch/liability waiver form, we will send a Designer to the proposed site to
determine an accurate cost projection.
Back to top
- How do I obtain a cost estimate if I want to upgrade or relocate my electric
service?
- Before calling WPS for an estimate, we suggest you contact
a local electrician to review upgrade requirements or changes that will be
needed on your electric service facilities. Once you get the information from
your electrician, call WPS to apply for an upgrade or relocation estimate
and provide a site sketch/liability waiver form. A Designer will be assigned to your
request and provide you with an estimate.
Back to top
- What if I need to meet your Designer on site to discuss the electric/gas route,
how do I contact him?
- If you need to meet our designer on site to discuss the gas/electric location and
routing of facilities, email New Service Installation with your
request. If an application and a site sketch/liability waiver form have been
submitted previously, we'll take your request and pass it on to the Designer.
Back to top
- Do you have any incentives or rebates for new home construction?
- WPS does not offer an incentive program for new homes.
There are programs available through Focus on Energy. Call 800-762-7077 to find
out what programs are available for new homes or visit their website at
focusonenergy.com
The Focus on Energy website will walk you through the various programs and
eligibility requirements.
Back to top
- My heating contractor has suggested that we convert to natural gas for heating.
Are there any conversion requirements?
- The Public Service Commission of Wisconsin mandated that all homes built prior
to 1978 must meet a minimum Structural Compliance requirement. These
requirements include minimum levels of insulation in the attic and sill boxes.
The exterior windows need storm windows and/or double pains of glass. The
weather-stripping around the doors and windows must be in good shape. You can
call WPS to have a compliance appraisal completed on your
home at no cost to you.
Back to top
- Do I need an electrical inspection of my wiring before you install my service
and set the meter?
- An inspection by a State of Wisconsin certified inspector is required for all
new one and two family homes. For service relocates and service upgrades,
requirements by local Municipalities vary. Always check with the local
Municipality to determine their requirements for either an inspection or a
Certificate of Compliance from the electrician.
Back to top
- I have permission from my neighbor to cross their property with electric service
for my home. Will I need something in writing from him?
- Before we can install electric service across your neighbor's property, you need
to provide an Easement. This legal document specifically gives the legal land
description and the description of the area needed to install our gas and/or
electric facilities. Once this document is signed and notarized, it will be
recorded as a permanent record in the local courthouse. When that process is
complete, we can move forward with your project.
Back to top
- During the winter months, are underground service installations possible?
-
Yes, we will install underground facilities all year long. However, there will be
additional charges due to the increased costs associated with construction during the winter
months. Additional "Winter Construction Charges" will be charged between December 1 and March
31, to help recover the additional costs associated with underground service installation
during the winter months. (For Michigan customers, the effective dates are between November 15
and April 30).